Full-Time Construction Supervision and Contract Management for the Vasilikos–Nicosia Water Supply Infrastructure: 35.7 km of Ductile-Iron Pipelines up to 800 mm and a 10,000 m³ Reinforced-Concrete Storage Reservoir
Client: Water Development Department, Cyprus
Estimated construction cost: Over €9 million
Project overview
Our company provided full-time, on-site construction supervision and construction and contract management for Phase A infrastructure transporting desalinated water from the Vasilikos Desalination Plant towards Nicosia. The assignment covered three major sub-projects forming part of this strategic water-supply system.
Main infrastructure
- Sub-project A3: Construction of the reinforced-concrete Stavrovouni Reservoir, with a useful storage capacity of 10,000 m³.
- Sub-project B1: Installation of 16.5 km of 800 mm-diameter ductile-iron pipeline.
- Sub-project C1: Installation of 19.2 km of ductile-iron pipelines, with diameters of 800, 700, 600, 450 and 200 mm.
Full-time construction supervision
A multidisciplinary supervision team was stationed full time on site to monitor the execution of the works. Our responsibilities included verifying compliance with the approved drawings, technical specifications and contractual requirements; inspecting materials and workmanship; monitoring construction quality, safety, progress and programme; reviewing method statements; and resolving technical issues arising during construction.
Construction and contract management
Our company managed the construction contracts throughout their implementation. The services included measurement and certification of completed works; preparation and assessment of interim payment certificates; evaluation of variations, additional works and revised quantities; examination of contractors’ financial and time claims; assessment of requests for extensions of time; monitoring of programmes and contractual milestones; preparation of technical reports and recommendations; support during dispute-resolution procedures; and review of final accounts, final acceptance and handover.
Project period
The consultancy services were provided from April 2021 to 2025.