Waste-to-Wheel Pilot Test-Runs

The pilot test-run of the technologies developed in the context of
the Waste to Wheel Project was performed at Paphos
Wastewater Treatment Plant, on the 10th of October 2020. The
biogas Upgrading, Storage, and Refueling Unit (USRU) was
repeatedly tested in real world condition during Plant operation,
resulting in consistent performances between tests. The focus of
the test-runs was to evaluate the energy efficiency of the USRU
and the biomethane quality. It was observed from the results that
methane purity of the upgraded biogas was on average 92.94% .